Major Projects

ALL

Apartment, Business & Commercial complex

Logistics center & Automated warehouse

Industrial Plant , Factory & R&D center

Data center & Other facilitys

Overseas project

Geomdan 101 Station Area Next Complex
Site Address
Wondang, Seo-gu, Incheon
Project Scale
RC1 BL: B2 ~ F29, 5 buildings C1 BL: B6 ~ F20, 3 buildings C9-1 BL: B7 ~ F37, 1 building C9-2 BL: B7 ~ F35 , 2 buildings
Project Duration
2023.08 ~ 2027.12
Detailed
Construction Work
Electrical construction
Songdo American Town The Sharp
Site Address
Songdo-dong ,Yeonsu-gu, Incheon
Project Scale
B3 ~ F50~70, 3 buildings Apartment 498 units, Officetel 661 units, Commercial 147 units
Project Duration
2021.09 ~ 2025.06
Detailed
Construction Work
Mechanical construction
Samseon 5th district redevelopment project
Site Address
Seongbuk-gu, Samseon-dong, Seoul
Project Scale
B4 ~ F18, 19 Buildings
Project Duration
2024.01 ~ 2027.03
Detailed
Construction Work
Electrical construction
Dunsan The Sharp Elif
Site Address
Yongmun-dong, Seo-gu, Daejeon
Project Scale
B3 ~ F12~33, 8 buildings
Project Duration
2022.12 ~ 2025.01
Detailed
Construction Work
Mechanical construction
Project Project Duration Detailed
Construction Work

Seocho-dong Seoul, Complex facility

23.09 ~ 25.03 Electrical, Mechanical

Geumnamro 5 ,Gwangju dormitory

23.02 ~ 25.07 Electrical

Galwol-dong Seoul, Near station youth housing

23.01 ~ 25.05 Electrical

Wondang Lotte Castle SkyL

22.12 ~ 24.06 Electrical construction

THE SHARP Geoje DICLIVE

21.09 ~ 23.12 Electrical

Pangyo Techno valley 2nd Studio

21.02 ~ 22.02 Electrical, Mechanical

Sasong-dong Yangsan, 2nd Apartment project

20.11 ~ 23.04 Mechanical

Geomdan Incheon, AA11 Block Apartment

20.05 ~ 22.06 Mechanical

Juyeop-dong Ilsan, Complex facility

19.07 ~ 20.09 Electrical

Godeok Gangil, 14th Public Apartment District

18.11 ~ 20.10 Electrical
icon_arrow_top
×